Behind The Build

The latest construction updates from the Westfield CC Club Master Plan. More information will be shared as key milestones are achieved. Click on the Titles below for more information.

April 15, 2025

Clubhouse Wall Prep & Foundation Walls

Clubhouse Wall Prep, Foundation Walls, Pool House Layout, Cart Barn Set Up 

April 08, 2025

Poolhouse Building Pad, Foundation Walls, Golf Setup & More

Poolhouse Building Pad, Clubhouse Foundation Walls, Golf Setup and More.

April 01, 2025

Foundation Walls, Parking and More

Foundation Walls, Parking, Cart Path and Retaining Wall Footers

March 25, 2025

Parking and Cart Path Preparation, Retaining Walls and Foundation Walls

Parking and Cart Path Preparation, Asphalt, Sidewalks, Retaining Wall Excavation and Foundation Walls

March 18, 2025

Clubhouse Walls, Foundation Wall Backfill and More

Foundation Wall Backfill, Grading, Clubhouse Walls and Waterlines

March 11, 2025

Main Drive, Building Pad, Water Main, Curbs

Main Drive, Building Pad, Water Main, Curbs and Cart Barn