2/18/2025 3:37:25 PM by Mallory Syx

Footer Progress, Site Grading & Aerial View

Footer Progress, Site Grading, Building Pad Aerial View and Mud Mat

Read More

2/11/2025 1:28:54 PM by Mallory Syx

Site Grading, Haul Roads & Footers

Site Grading, Mud Mats, Haul Roads, Rebar Footers and Storm Install

Read More

2/4/2025 4:00:00 PM by Mallory Syx

Service Trench, Site Grading & Building Pad

New Service Trenches, Site Grading and Building Pad

Read More

1/6/2025 3:52:00 PM by Shannon Showers

Clubhouse Footer & Pavilion Demolition

Clubhouse Footer Demolition, Site Grading and Pavilion Demolition

Read More

12/17/2024 11:09:31 AM by Shannon Showers

Clubhouse Demolition Continues

Clubhouse Demolition continues, Pool Demolition and Backfill complete, Asphalt Removal and begin Retention

Read More

The latest construction updates from the Westfield CC Club Master Plan. More information will be shared as key milestones are achieved.

Footer Progress, Site Grading & Aerial View
Site Grading, Haul Roads & Footers
Service Trench, Site Grading & Building Pad
Clubhouse Footer & Pavilion Demolition
Clubhouse Demolition Continues